Planning Schedule of Pipe Fabrication
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Dear Shahzad
The best way to develop the detail schedule for 75000 dia inch plan you first of all need to develop a WBS to lowest level it may be like area wise/unitwise then seprate by material such as CS / SS / AS etc, then you can further break up to small bore and large bore and extra large bore such as less or equal to 1.5", 3" to 24" and more than 24" so on. Now at this stage is better to cevelop the package of no of isometrics and set up schedule to monitor the progress and develop s-curve
For that quantity of pipe spools I would recomend that you first break it into packages according to the requirements of your construction programme and fabricators capability. 500 drawings should equate to about 25 to 50 packages.
Then set up schedules (table format) by drawing to track the progress of fabrication with % complete recorded for material delivered, processing (or cutting), fitup, welding, testing and delivery to site (or however you see fit). You can drive S Curves from this data and use it to update the high level activities in your schedule for the piping packages.