Project After Suspension

P
Pranab Kumar Deb 👤 Member for 19 years 4 months

Dear Sir,

i Hope to make it thanks for the support , it really feels great when u spend some time with peoples of same profession they understand exactly what u are speaking about .

regards

deb

C
Charleston-Joseph Orbe 👤 Member for 20 years 11 months

Deb,



That settle it, your love for the challenge.



Go for it with all your heart, with all your love for planning, contract administration, procurement.



Believe me, it is very seldom this kind of opportunity will come into your life. You can always look back someday and say "I DID IT MY WAY" same as the popular song "My Way".



Cheers,



Charlie

D
David Moses 👤 Member for 21 years 7 months

Hi there,



I did not mean, dont take the challenge.



But, think twice!



Of course every project improves experience, adds new value to your professional belongings.There is no objection for this.



But while you are working within such a challenging project, dont forget to sum enough money for the rest of your life.



Otherwise you will be experienced but without money.



Think twice Deb think twice,



Regards

C
Charleston-Joseph Orbe 👤 Member for 20 years 11 months

David, Deb



Go for it, take the challenge. The money may not be worth it, but the experience and confidence will take you around the world.



And if you will have the proper attitude, believe me the universe will be yours for you to go for an adventures, meeting different people, getting fat check.



Go deb go,



Cheers,



charlie

D
David Moses 👤 Member for 21 years 7 months

Hi there,



Of course take the challenge.



But if it is worth to? I mean if you are being paid accordingly.



Best Regards

C
Charleston-Joseph Orbe 👤 Member for 20 years 11 months

Pranab,



Take the challenge. It is very seldom that you will encounter this kind of work ambiance.



Believe me, you may be hard pressed to arrive at a solution to the situation you are in, but, you will emerge a stronger planner with regards to planning, contract administration, costing.



Cheers,



Charlie

P
Pranab Kumar Deb 👤 Member for 19 years 4 months

Dear Sir,

ya its tough add to this we have a roofing system according to canadian systems which the local authorities ( following russian codes ) are not willing to accept , and this whole activity ( steel structure roofing + cladding ) is a highly critical activity.

regards

deb

B
Brennan Westworth 👤 Member for 23 years 3 months

it sounds like your client is quite unreasonable, looks like you are going to be in for a challenging project.

P
Pranab Kumar Deb 👤 Member for 19 years 4 months

Dear Mr. Charleston ,

Ya EOT is already an issue as we demobilized after the suspension , also all procurement activity were cancelled ( As it was illegal to work for us in this period due to a local court order ) now we have to completely restructure the procurement (which is a big problem here ) now the client while accepting a EOT equal to the suspension period is not accepting the EOT due to restructuring the Procurementa and the Remobilization period. There are other issues like subcontractors asking exhorbitant increase in prices. So i am also looking to Value engineering for materials which were initially to be outsourced from Europe with that from UAE.

regards

deb

C
Charleston-Joseph Orbe 👤 Member for 20 years 11 months

Hi,



Me too, i always thought it was Mr. All the time I was wrong with regards to Miss Dana.



Anyway, Pranab, just suspend the schedule equal to the numbers of months it was suspended.



There was a lot of precedence that you will get the required EOT.



However, but, however, sometimes / maybe the number of months may depends on what the top brass of your company will agree with your client’s top brass. so the final EOT will depend on your boss instructions.



Cheers,


P
Pranab Kumar Deb 👤 Member for 19 years 4 months

hello miss dana ,

thanks for the correction actually one of my colleagues who is a jordanian and a good friend already told me that this is Miss dana

regards

deb

P
Pranab Kumar Deb 👤 Member for 19 years 4 months

Dear Mr. Dana & Mr. Victor,

Thanks for the options u have given me i will try both ways and let u know the results

regards

pranab

D
Dana Qandah 👤 Member for 19 years 10 months

If all the activities are suspended just reflect it in the main calendar by nonworking days, if the suspension is only in limited activities, create a new calendar and link the infected activities with this calendar.



Hope this will work with u



Dana




V
Victor A 👤 Member for 19 years 5 months

Put new activity in the beginning of your project - Start - September 2007, Finish - February 2007. Activity Description - Delay. Reason is ....

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts