Resources on Summary Bars

M
Mohamed Ibrahim 👤 Member for 20 years 6 months

David,



The easy way is to insert an activity and change the type to WBS instead of task and then schedule, there is no need for any links and this will be similar to the summary bar and you can assign resources to this activity with your lag and duration for each resource as normal.





Kind Regards

Mohamed

G
Gün Göksu 👤 Member for 21 years 2 months

try and use a hammock activity.

start-start to first activity in schedule,
finish-finish to last activity in schedule.
activity type: hammock.

it is good practice to link the start and ends to milestones.

Gün.