Converting project planning units

M
maurice x 👤 Member for 19 years 5 months
A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Maurice,

when you copy a project A with planning unit = days to a project B with planing unit = hours, P3 does not calculate the activities original duration from day to hours

you should use Global Change to divide activities OD by 8, and P3 will take care of all the rest of it

Alexandre

M
maurice x 👤 Member for 19 years 5 months

Scott,



This part I know, but that doesn’t change the OD/RD/LAG/FF/TF etc.



Maurice

S
Scott Hastie 👤 Member for 21 years 2 months

Hi there,



you could try copying the project, if you go tools,project utilities,copy.



you should be able to select a planning unit when you are selecting the copy To options. i.e hours, days, weeks, months



Hope this helps.



Scott


Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts