Actual earned quantity!! Not match with real situation!
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Check your autocost rule as well
BTW as .mktse suggested, seperate your activity and resources that will help to untangle the mess
Alex
Instead of resource lag, please consider the resource curve. I create one for concrete - 0% to whole period except the last one. So the curve is "flat" except the last day.
So no actual quantity until the concrete day and same day for the Actual Finish of this activity.