MAking Additonal progress Bar...
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Create a copy of exisiting schedule
Make it your target schedule
Display your target bar
Modify your target schedule or Current schedule that way the other wont change. Normally you modify your current schedule and maintain the target as a baseline
Good Luck
ALex