Hi Mr Paul,
Thanks for the peace of advice, I just want to clarify in part what is Free float.
Rodel
Total Float is the difference between the Early Finish and Late Finish, e.g. the duration a task may be delayed without delaying the end of the project
Fee Float is the difference between the Earliest Successors Start and the Early Finish of the Activity in question, e.g. the duration a task may be delayed without delaying a successor.