PROJECT SCHEDULE DURATION
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hi,
I clearly mentioned that it depends the level of details. But to find project completion date 20 days is ok..
You can develop activities like rafts in in 10 0r 15 zones, detailed vertcals & horizonatl of a typical floor and mutliply the duratioon eith combination of floors... core wall duration for atypical floor ,one or 2 activities for evelvators , 5- 6 actvities for external cladding and typical floor finsh will do the purpose... it will not more than 20 days.....
Cost loading , resources, loading etc... ofcourse will take time... full programm approval will take 6 month or more with many revisions....
thanks
weni,
if ur new to the trade, try to make a draft schedule as fast as you can (within one week or less).then present these schedule to the responsible persons(CM,PM,PIC,etc.).they will surely be giving a lot of comments and it will now be easier for you to take it from there. this will make the planning duration a little shorter.
And of course the complexity of the project
But bare min. is 20 working days
Alex
Weni;
It could take even longer depending upon which team players are available to you. A superintendent would be required to really be effective. A good strong knowledge of the construction drawings is reqd. Are u cost loading/resource loading the sched? What about enigneering and procurement tasks. A lot depends on most of these issues.
Good Luck.
Thanks. That could be of help.
Hi,
It depends which level of detailing you need!! emm mostly to arrive the durtaion of the project with minimum detailing you may reqiure 15 to 2o days