Discrepancy on % completed & Total Float
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
By solved this problems, i recommended you to execute "re-organize now" command 2 times before every time when you want to explain. sure it will solve your problems.
Sure you have any prolems,you can direct contact me. 012-2867713.
Both PCT and TF of summary bar are determined by various factors which can be control in Option - summarization.
However, settings may be overrided by parameter in each report template. Please check.
Further, to reduce the changing of these 2 value on screen during editing, stop the auto-scheduling function, hope help.