PERT functionality ???
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Dear David,
Thank you so much for your help!
Dear David
Thanks for the valuable information and clarify the difference of PERT (Project evaluation & review technique)and Primavera abbreviation
Tahir
Benny,
No, primavera has no probalistic capabilities. The recomended route is to use the "Pertmaster" product which reads and writes data to the primavera project.
(FYI in "Primavera speak" PERT stands for Primaveras Easy Relationship Tracking)