PERT functionality ???

B
Benny Lam 👤 Member for 19 years 11 months
T
Tahir Naseem PMP, CCE 👤 Member for 19 years 7 months

Dear David

Thanks for the valuable information and clarify the difference of PERT (Project evaluation & review technique)and Primavera abbreviation

Tahir

D
David Kelly 👤 Member for 21 years 7 months

Benny,



No, primavera has no probalistic capabilities. The recomended route is to use the "Pertmaster" product which reads and writes data to the primavera project.



(FYI in "Primavera speak" PERT stands for Primavera’s Easy Relationship Tracking)