Hi alex
Of course it our fault then, we pay him for 8 hours, as we plan to use equipment like truck for 8 hours per day, but if we work for 14 hours we pay him consequently
mimoune
Yes Mr alex
It is normal where you have industrial states. For day to day maintenance and specially during the shutdowns. Lot of equipemnt supply you the equipmemnt on hour rate + mob & demob cost. But in this case the rate is abvous high teh daily/weekly/monthly bases.
mimoune,
so if you only use the equipment for 2 hrs do you pay for 2hrs or the whole day??
Al
thanks Ronald
Ah ok, in our country we even rent equipment by hours!
mimoune
I believe that it all has to do with money. You pay for labor by the hour but you rent equipment by the day.
Hi expert
I suppose that my English is so bad that you did not understand the question?
My question, why for labour he uses hours, and days for equipments ?
mimoune
Create A Project With Hours Duration
P3 Default Is Day