Please find the following for Primaera Help menu



"At some point in the project, you may need to stop work on an activity for a period of time. Indicate this interruption by specifying suspend and resume dates in the Status tab of Activity Details.







Display Activity Details.



Click the Status tab.



In the Activities window, select the activity you want to suspend.



In the Status tab, enter a Suspend date.



When the activity resumes, enter a Resume date.



"



Good luck



Alex


S
Sean Moghimi 👤 Member for 19 years 7 months

Dear Alex



Thanks for the message. If you mean suSpend and resume, yes i mean the same, that sounds good. would you give me more advices on how to do it in V.5 plz.?



Regards.

A
Alex Wong 👤 Member for 23 years 4 months

Shahab



you mean subspend and resume??



if it is , then the quick answer is yes you can do that in P5



Cheers



Alex

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts