Thanks Alex.
Marcio Eduardo.
A plan value cannot change if the activity is already finished
And some planning condition is require in order to have the EV display correctly.
Ie. Actuals $ and Actual Hrs need to more than 0 in order to progress the activity.
You have to be careful with reverse a completed activity.
Suggest you copy the project and play a little bit prior to actually change the completed status
HTS
Alex
Im also with same problem!
Could anyone help, please?
Regards.