Sure Trak dates entering problem
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Dear musawar Shaikh
The intension of the software is to calculate the dates for you. When an activity is added the dates will be calculated for you by entering a start date of the project and then adding relationships amongst the activities. You may apply constraints to activities to prevent the tasks before or after dates.
I suggest you read up on the basics of Critical Path planning as a start to understand the basics of software such as SureTrak and then read the manual or a book obtain some training in the software.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au