resource levelling

J
John Moss 👤 Member for 22 years 4 months
J
John Raper 👤 Member for 22 years

John



Have you tried dividing by 8 or 40, and showing the time window in days or weeks?



Hope this helps

John R

P
Paul Harris 👤 Member for 25 years 2 months

There are a couples place in P3 where there is a 9999 limit including activity duraton which restricts the total duration of a project.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au

D
David Kelly 👤 Member for 21 years 7 months

John,



I’ve always just divided the resource requirement and the resource availablity by a factor of 10.