Linking of P3 data base to AutoCad.
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
In P3, filter out those activities which will be in chainage diagram by code.
In autocad, prepare a macro including: -
- link to P3 selected activities and look for activity type, duration and dates.
- prepare the axis of the diagram, ie time scale and chainage scale
- shape of each object determine by activity type
- size of the polygon depends by dates and duration
- for color, may by some activity code
MKTSE