Hi
If you check out and follow reply of the 07-Sept..
You should then be able to export the data from P3 in an Excel format.
The data will be by manhours by time period (i.e. how you have specified - weekly/monthly etc).
You then need to add rows etc and set up the standard calculations for working out percentage complete etc.
Regards
John
Hi
Try the method suggested by us. That will give you a good S-Curve facility, especailly in Layout View.
Alex
I would like to extract percentage completion distributed by time-period from Primavera. Can anybody help me?
Many thanks in advance.
Hashim
Hi
To view in Layout you will need to go into "Page Setup" and tick the box "Resource/Cost Dispay".
The layout will display the Histogramme / Curve at the bottom of the schedule. It is verry effective for a high level plan especially if displayed on a single sheet.
To get the data as you require you need to use the "select" and "dispay" buttons, can be a bit of a problem when first setting up.
Regards
John
Just 2 points as well:
1. You can view the S-Curve in Layout as well (View - Layout)
2. Remember to you save period actuals
Then you S-Curve will have a more accurate result in Earned Value and Actual.
This concept is differ from MSP
Alex
Hi
Q1 : How do I extract data from P3 (or let P3 generate) to create S-Curve.?
Try: Tools / Tabular Reports / Resource / Loading
You will need to set up the P3 window options with your resources / selection etc. Once run it will generate a stread sheet format that you can make into SCurve / Histogram etc, and save as excel format etc
Or try: Tools / Tabular Reports / Resource / Tabular
This will give you a hard copy of data, that you will need to key into a Curve etc.
Q3 - Paste in Excel & gnerate S-Curve (progress %) as Excel Chart.
Yes - see above - just add calculations to the excel spread sheet.
Q2 : Can P3 do it per WBS/Activity Codes or discipline etc.?
Yes, its all done when you set up the P3 windows, its a bit messy first time, but try using the P3 Help option if you get stuck.
Q3 : How do I generate Manpower Loading (unlevel) in P3.
Use the above, the info generated is in Man hours so just set up your excel spread sheet with a simple calculation.
regards
John