Splitting / Suspend /Resume Activity

C
Christian Adrian De Vera 👤 Member for 23 years

using "suspend and resume date" should be dealth with caution, you can only use it on an activity which is active and has been affected with arising events not to prolong the schedule...



Cheers...

K
Karim Mounir 👤 Member for 20 years 2 months

Splitting : select the activity u want and right click on it and select Dissolve / Extract.



Press F7 to show the bottom activity form

Suspend / Resume : select the activity in which u want to apply suspend or resume date then click on "Dates" then select the "Suspend" or "Resume" date.