Thanks William
I am on vacation at present and will try your suggestion when I return to the office next week.
Thanks again.
Trevor Lyle
Hi Trevor,
To clear variances (per activity):
1. check that your remaining duration (RD) is not equal to 0
2. if RD is 0, reset your progress PCT % to 0 (note previous figure)
3. increase your original duration (OD) and enter orig PCT %
4. repeat items 1 & 2 until RD is at least 1
5. click Res (Resources) Tab
6. edit the figure "At Completion" and make it equal to "Budgetted Quantity"
7. Click OK.
Hope this helps.
William