Hi Berke,
P3 does not work this way.
ATD & ATP are computed from Activity PCT. Not vice versa.
Best regards,
Jorge
Hi,
Activity PCT field in Activity Form is a user input field (where u specify how much is activitys schedule percent complete), and not a calculated field.
Again, resource rate x resource actual quantity = resource actual cost (and not PCT)
However, this multiplication takes place and you get actual cost of resource as actual to date in cost field of activity..
As per this actual cost, you will also get percent complte & percent expended as well in same window, taken from activity form.
regards
sonia