Update Target - New Activities

N
Natasha Lord 👤 Member for 22 years 4 months

I tried a new test schedule so the default items would show up in the Project Utilities/Update, and I had 3 items unchecked that needed to be checked. So it’s all working now, thanks for the help.

R
Ramesh Kavassery 👤 Member for 21 years 7 months

Hi !



I just tried the update target procedure for added as well

as deleted activities. Both seem to work fine.



Keeping the target file closed is indeed necessary, which

is not the problem. Checking the "For activities not in the target...." also is necessary and correct.



In the options, there is "Store" under which you have 2

sub-options : Actual Dates & Current Schedule dates. Make

sure they are not checked if you want to stop the target

file from getting re-scheduled.



Try the procedure again and post back in case any problems.

Good luck !

R
Raja Izat Raja Ibrahim 👤 Member for 21 years

Hi,

FYI, Never change target schedule unless U want to change the layout for presentation.

However If U going to add new activities, U have to copy the Updated schedule as the Target rev2 and another copy for monitoring progress.

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts