Resource relationship within a task
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Good day
Thanks for info.
I will check & dload their demo.
Thanks again.
Redzuan
Primavera is task based, so you cant show linking relationship for resources in P3. you can think of Spider Project Software for that option. you can find a demo copy from their website.
Good day
Thanks for the input.
So, the solution you mention is the ONLY way to link resources within a task??
My post/question arises because during my presentation to my boses (yesterday), one of them mentioned that linking resources in an activity is possible --> to achieve a logical Manning Level.
The way he said it, its like linking task by using relationship line.
Is this possible?
Thanks
Hi Redzuan Samsudin ,
In Primavera Project Planner P3 we have an option in the Resource window(used for adding resource to task),for Resource Lag & Resource Duraton.By the proper use & adjustment of these you can for eg. have one resource at the start of a task, another at the end etc.
Hi,
Would not recommend, however, the thing which are looking for can be managed easily if you make resources as activties and then link them as you want. You can certainly make a hammock to umbrella these activities/resources.
Regards
Rashid
Hi Redzuan Samsudin,
In P3 you can choose a task as "Independent" which based on resources. I think, it is a way to solve your problem.