You cannot do this in any Activity layout in P5, BUT you can do it in the resource asignment view. This is the equivalent of "Format Organise" by resource in P3 3,1.
Thanks Julie and David. I was able to get the required column in Resource Assignments window. Its a bit weird, the way this software works, but nontheless things are working out one way or the other, so I am a happy customer again, atleast for the time being.
Cheers
Zafar
Zafar
You need to add the column ‘budgeted labour units’ to your layout. There are 3 types of resources in P5 - labour, non-labour and materials. And unfortunately you need to use UDFs to get the total budgeted units in a column.
Cheers
Julie