Mandatory or Early constraint...
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Thanks Nigel !
Actually it could mean that my sbucontractor is keeping some float in his pockets or maybe (and I think thats the case) hes a bit confused in his sequence of scheduling.
Thanks anyway guys for your participation !
Nicolas
From your reply, it sounds like the contractor has forced his programme to meet the end date. Without the constraints, it finished earlier. This PROBABLY means that he has a lot of float that he is hiding - or making an allowance for lateness.
Done similar things but not with mandatory constraints.
Nicolas
I would like to clarify what a Mandatory constraint does to a P3 schedule.
A Mandatory constraint stops float (negative or positive) calculating through the task with the mandatory constraint.
A Mandatory constraint in the middle of a chain will break the chain and the float calculations will start again at the constraint. Normally this is not a good practice.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
So I removed all those "Mandatory constraints"...they all had predecessors...
But result is, the sequence has changed and Finish date is 2 month earlier.
And all those milestones are now spread out.
This schedule must be rework...
Bon Chance
I Understand and I am agree !
Thanks, Ill check it out right now...
Nicolas
A mandatory constraint is not as flexible as an early constraint. A mandatory constraint will affect the programme logic a lot more than an early constraint.
If your contractor has used that many mandatory constraints it suggests that there is a problem with his logic and he is using the constraints to force the logic to work.
If it was me, I would make a copy, remove a section of the constraints and re-schedule. See how far out his logic is.
I generally use two mandatory constraints - Project Start and Project Finish and then only to force the float.
Cheers
Nige