resource calendars

B
Benny Lam 👤 Member for 19 years 11 months
P
Paul Harris 👤 Member for 25 years 2 months

Question 1



Benny



Each resource may only have one calendar. For the resource to schedule with a calendar it must be Independent or Meeting Task Type.



Question 2

You may use Global change to change the quantity o resources. You need to understand the Autocost rules before you use this function.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au