Problems with different schedules

J
Joao Ribeiro 👤 Member for 23 years 2 months

In Suretrak, I think you must change the activity type to "Independent", in P3 I don´t remember now, but there is something similar with other name.

Anyway, I think the cost will be the sum of eight hour of one resource with the nine hours of the other (if both work on the same activity).



Cheers.

M
Marcio Sampaio 👤 Member for 20 years 7 months

Thanks a lot ... but read again:



"I created a different schedule for these resources, showing 9 hrs a

day and 6 days a week, but even if the program asks me if I want to

re-calculate the costs, it will always show 8 hrs a day for all

resources."



Regards

D
David Moses 👤 Member for 21 years 7 months

Dear friend,



why dont you try to create two different calendars.one for 8 hrs a day and the other for 9 hrs a day.



I hope this will help.

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts