Merging Schedules w/ Different Planning Units

K
Kashyap Mothali 👤 Member for 21 years 2 months

I guess a Global Change would solve the trick but it wouldn’t apply to ’lags’.



Thanks for the suggestion,



Kashyap

D
David Kelly 👤 Member for 21 years 7 months

There are two reasons why you would merge projects with different planning units.



1) Summary reporting, i.e. the output project does NOT need to be scheduled. In this case the dates that come across for the "mixed" planning unis are correct and the summary project should NOT be scheduled.



2) Further scheduling. A global change will be required to change the durations of either the "daily" or "hourly" activities. This MUST be run before you schedule.