progress line through the summary bar
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
MSProject simply the best. You can show progress line on summary bar. Suggest to plot summary bars in MSProject and display the progress line, if you really need to do so.
Regards.
Think u cant.
The "color" progress will show on the summarized bars (in Format,Bars...). I dont know if that is an option for you.
but once you summarise the bar it will not come
Hi Prem,
The progress line option is available in format-sight lines-progress line,
In that you will get 2 options, one with the difference between current and target finish dates and the other by connectng the progress points,
Cheers,
FMV
Noway