Just now I have seen your question, it seems to be an old posting, anyhow let me try to answer your question.



you can display the resources quantities for an activity in resource table. to do this, click Resource/Cost Table icon from the menu, then click select button, choose the three resources one by one under the "Low Value Resource". That’s it. you can see the resources quantities against each resources in the table(Note if your activities are overlapped, you will get summarized quantity for the resource in any specific day/week/month)



HTH

B
Bijaya Bajracharya 👤 Member for 21 years 3 months

Christian,



Can you be a little more specific in steps? If you have, say, three types of resources, when you get budgeted quantity, P3 gives you the total quantity of all the three resources. What you want is quantity of each resource separately.

C
Christian Adrian De Vera 👤 Member for 23 years

Hello Bijaya



What you can do is create a layout for your resources then label your bars with their corresponding quantities..



HTH



Christian

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts