P3 to P3e convert.

A
Alex Wong 👤 Member for 23 years 4 months

I suggest you have to test run it first for P3e-P3-P3e



I cannot see a great problem if your import and export setup is correct. Meaning the updating code, resource code, activity code, calenda, WBS.



P3e - P3 should be simple All information should be there

P3 - P3e require a bit of co-ordination between you and your sub becasue P3 only have limited activity and project code (and limited lenght as well) you have to do some global change to convert it to your master schedule

Regards

Alex

S
Steven Oliver 👤 Member for 23 years 7 months

Basically, dont go there.



P3e has so many things which P3 doesnt.



You will spend massive amounts of time checking the results.

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts