Extra works in P3

H
Hannes de Bruyne 👤 Member for 20 years 10 months

For me this is very clear - Change of scope is part of the job, so it must be shown in the timeschedule. Showing it in the contract schedule (target) is an other thing, because this schedule was agreed with the client/engineer. If the client agrees on changing the contract schedule, only than you can modify the contract schedule (but not to often). And send this modification to the client in writing!!!!!



Changing the scope changes money and time, what clients like to oversee. The timeschedule is the best instrument to keep record of this.



Hannes

E
Edgar Ariete 👤 Member for 20 years 10 months

there you go again, it’s just like the total number of activities with the corresponding percent progress...

J
James Bridges 👤 Member for 21 years 7 months

If the variations have a significant affect on the critical path, it may be that the best solution is to re-baseline the programme with the agreement of the project team and the client. At least then you have a realistic target in which to measure progress against.



Regards,

S
Steven Oliver 👤 Member for 23 years 7 months

Create a new grouping "Variations", and add activities relating to the additional works. Some may have immediately apparent impact on your existing schedule, or possibly simply the volume of changes can be the cause of an impact to your schedule.



Until such things are included in the schedule it is very difficult to quantify the extent.

E
Edgar Ariete 👤 Member for 20 years 10 months

create another plan & a new target for approval? or treat it separately?

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts