levelling of resources

S
sunil kumar 👤 Member for 20 years 7 months
C
Christian Adrian De Vera 👤 Member for 23 years

Hello,



If your not satisfied with automatic levelling perhaps you could also do the manual levelling before you try to schedule it... but make sure you back-up your copy first before doing any drastic changes just to make sure..



Cheers!



Christian

P
Paul Harris 👤 Member for 25 years 2 months

If you wish the schedule to remain levelled then you should not reschedule it.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Book Publishers, Training & Consulting

www.eh.com.au