Scope changes and P3

C
Charleston-Joseph Orbe 👤 Member for 20 years 11 months

Hello Vanessa,



Yes, you have to include the changes in scope of work, variation order, etc., in your schedule.



Generally, if you are using Work Breakdown Structure, you will add a new WBS- 50.000 Variation Order, Changes, etc. You can further make a new sub-level: 50.100 Provisional Variation Order, 50.200 Extension of Time (in case you will be going into extension of time, etc.



The above is an example only. I hope it help you.



Cheers,



charlie


R
Raja Izat Raja Ibrahim 👤 Member for 21 years

hi vanessa

if we looked at the contract, if the activities is out from the scope we add under title VO or addtional scope but if it is activities lefted behind u can see at below post how u going to add activities.

Forum

Primavera Project Planner - P3

-Update target Function

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts