first you have to create a target schedule from your current schedule, if you already have a baseline/target schedule, make this schedule to be available in the current schedule layout
i.e
Tools->Project utilities->targets and choose the schedule you want to compare.
then only you can get those figures that you wanted to get.......
regarding global change it depends on the availability of row in global field i believe you can use many conditions but use it wisely.
Hamid,
It seems like you are undergoing a self-learning process like me. I have also faced problems like these, which pushed me to get help from books.
I would strongly recommend that you read the book "Planning Using Primavera Project Planner" by Paul E. Harris.
I have found his books really helpful in accomplishing essential tasks like comparing actual with target progress.
Good Luck.