Tracking changes

Y
Yves Trudel 👤 Member for 20 years 10 months
S
Sunil Kumar 👤 Member for 21 years 2 months

Try This, Make a copy of yourr target programme and have a update done by clicking tools update progress. This gives you the percentage on your target programme or the planned percentage as on data date. Use this file as your taget in your update programme. Compare the progress of your target which is planned vs your updated progress.



Trust this helps



sunil

S
Sukumaran Subaramaniyan 👤 Member for 21 years 3 months

Yves,



Export the Target Resource % Comp, Current Resource % Comp and Custom Data Items to spreadsheet(.WK1) file or database(.DBF) file.

Do the necessary changes and import back to P3.

Then filter according your requirement.



HTH

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts