50% of workforce on non-work days

R
Raja Izat Raja Ibrahim 👤 Member for 21 years

ya...u doing the right way using excel then import..i forgot about excel... U can do automtic caculation using excel formula..then import the file takes a minute to do that...

K
Katalin Hovanyi 👤 Member for 23 years 1 month

Thank You Ibrahim,

I was afraid that I neet to burn a few night candles to complet this changes or go back to do a lot of things in Excel.

R
Raja Izat Raja Ibrahim 👤 Member for 21 years

dear katalin,

to make it 50% resource in non working days as u said absolutely cannot be done unless at first setup the file u select planning unit in hrs...the other way, u can define every activities that working in non working days then u have to deduct 50% using global change or manual calculation. Its little bit tedious...to select one by one from the budget cost.

regards

K
Katalin Hovanyi 👤 Member for 23 years 1 month

Thank You Bill,

Can You be a little bit more detailed. The resource curve based on duration percentage, so how can I hit the non-work days with the half workforce for hundreds of activities with different start date?

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts