Planning Engineer, CEM Estero S.p.A (Qatar), New Doha International Airport Project

START Date

- Assist the Planning Manager & Project Manager in the preparation of Master Baseline Schedule – New Doha International Airport Project Package.
- Attending in the Contractor’s Weekly Meeting with the Client (NDIA), Management (Bechtel), and other contractors’ representatives to discuss the whole project matter, issues and concerns.
- To prepare detailed schedule for the project scope of works and Change Orders considering main factors such as time-frame, milestone dates, manpower, and resources needed.
- To maintain the Baseline Master Schedule and to modify it if revision is requi

Planning Engineer, Target Engineering & Construction Co., Extension of Refinery Ruwais UAE, Sea Water Intake Project Ruwais UAE, Olefins ProjectQatar

START Date

·          Preparation of Base Line Schedule considering scope of work, agreed milestones and constraints outlined in contract documents.

·          Preparing Project Planning, Progress Monitoring and Invoicing Procedures, Planning Package, along with all required formats and getting them approved from Client.

Planning Engineer, Murray and Roberts Middle East, Salam Resort Hotel and Conference Centre, Bahrain

START Date
END Date

Salam Resort 5 star Hotel & Conference Centre. 7 Hotel Villas, 6 Royal Villas on island. 9 road bridges, associated roads and landscaping.

Procurement and construction planning, design coordination and EOT claims.

Planning Engineer, Star Group, Aviation Building

K
Khalid khan 👤 Member for 12 years 9 months
START Date

 Preparation of Baseline Master Schedule and Recovery programmes in Primavera P6.  Coordinate and Liaise with Project Managers to update the detailed work program and ensure interface issues.  Prepare programs and other detailed information necessary for substantiating Claims and provision with regards to planning and programming to the Commercial department.

Planning Engineer, Star Group, Aviation Building

K
Khalid khan 👤 Member for 12 years 9 months
START Date

 Preparation of Baseline Master Schedule and Recovery programmes in Primavera P6.  Coordinate and Liaise with Project Managers to update the detailed work program and ensure interface issues.  Prepare programs and other detailed information necessary for substantiating Claims and provision with regards to planning and programming to the Commercial department.