Project Controls consultant, Arcelormittal Dofasco, Boiler Power Generation

Project Controls consultant, Arcelormittal Dofasco, Boiler Power Generation

START Date: 
January, 2019

Project Controls for ArcelorMittal Dofasco on a Boiler Power Generator Project

Experience Hours (Planning & Scheduling): 
36300
Consultant - Shutdown Schedule coordinator, Arcelormittal Dofasco, Maintenance Resource Scheduling - Quintiq

Consultant - Shutdown Schedule coordinator, Arcelormittal Dofasco, Maintenance Resource Scheduling - Quintiq

START Date: 
January, 2013
END Date: 
July, 2018

Develop training and documentation for a maintenance capacity utilization software.  Train mentor and coach users on the scheduling tool.  As a team member improve the product for easy use by the users and intergation with MSProject and the current CMMS system.

Experience Hours (Planning & Scheduling): 
40000
Experience Hours (Forensic Analysis): 
40000
Construction Project Planner / Senior Planner, lockerbie and hold, Potash Mill

Construction Project Planner / Senior Planner, lockerbie and hold, Potash Mill

START Date: 
March, 2012
END Date: 
November, 2012

Current Role

senior planner / Scheduler for a construction site responsible for the updating and further development of the schedule.  Ensure the schedule is current and truely represents the work in the field.   Help the management team understand and use the schedule and tools available to manage the project to a successful completion.

Senior Project Controls Coordinator, AMEC, Bruce Power Unit 1-2 Restart

Senior Project Controls Coordinator, AMEC, Bruce Power Unit 1-2 Restart

START Date: 
March, 2007
END Date: 
March, 2012

Develop and maintain Project Control measures.   Ensure schedulers are following the schedule procedures and rules applied

Project scheduler - Coordinator, Dofasco Inc, Outage schedules for steel industry

Project scheduler - Coordinator, Dofasco Inc, Outage schedules for steel industry

START Date: 
May, 1980
END Date: 
February, 2006

Outage schedules for business units and major projects.   Used MS Project, Primavera and Open Plan Software.  Seek software to enhance outage processes