Project Planner

Project Planner, Abigroup, Adelaide Desalination Project

START Date: 
June, 2009
END Date: 
December, 2010

Worked as an Intake and Outfall System Planner to build new 100 GL/year Desalination plant in Adelaide - $860million D & C contract.
Scope of work for Intake and Outfall system includes the Design and Construction of:
- The seawater Intake/Outfall tunnels (1.4km & 1.1km long, internal diameter of 2.8m) and structures (cross connection risers), and pipelines
- The intake pumping station
- Outfall Shaft

Site Based role

Project Planner, Cameron Ltd, Bacton

START Date: 
June, 2013

Current Role: Project Planner

·         Establish & maintain an effective Project Programme using Primavera P6.

·         Provide support to management for all planning functions ensuring that issues within the programme are highlighted and understood.

Project Planner, ACC, Princess Tower, 107 Floor Tower

START Date: 
May, 2004

Working as a Project Planner for PrincessTower(107 storey). World’s Tallest Residential Tower at Dubai Marina. 

Job Function      :           Making Base Line Programme (18000 activities).updating the Program, Review Sub Contractor’s Programme, Resource Loading (Man-hours, Quantity & Cost). Cash flow, Histogram, Weekly & Monthly Reports.

Project Planner, Gamuda - WCT, Infrastructure

START Date: 
July, 2005
END Date: 
February, 2006

Projects Experience :

  • Dukhan Highway – West Contract, State of Qatar. Contract Value : USD202.70 million
  • New Doha International Airport, Package 10: Airfield Paving, Tunnel & Detention Ponds, State of Qatar. Contract Value : USD 485.95 million
     

Project Planner, Cebarco - WCT, Building and infrastructure

START Date: 
October, 2002
END Date: 
July, 2005

Projects Experience :

  • Bahrain Racing Circuit, Kingdom of Bahrain. Contract Value : USD147.89 million
  • Highway Link to Durrat Al Bahrain Development, Kingdom of Bahrain. Contract Value : USD 46.45 million
  • North Manama Corridor Improvements Project (Seef Flyovers), Kingdom of Bahrain. Contract Value : USD 25.53 million


Tenders Involved :

Project Planner, WCT Berhad, Building and Infrastructure

START Date: 
April, 2001
END Date: 
October, 2002

Projects Experience :

  • Construction and Completion of Guthrie Corridor Expressway on Design and Build Basis. Contract Value : RM 386 million
  • The erection and Complection of 34 units 2 Storey Bungalows and 22 units Semi Detached at Lot 50888, Jalan Sulaiman 1, Taman Tun Dr. Ismail Kuala Lumpur.


Tenders Involved :

  • Bahrain Racing Circuit, Kingdom of Bahrain
  • North Manama Corridor Improvements Project (Seef Flyovers), Kingdom of Bahrain


Pre-qualification Tenders Involved :

Project Planner, Fluor Daniel SA, Multiple projects across multiple sectors

START Date: 
August, 1999
END Date: 
June, 2010

Various projects within project controls. Have done turnkey lumpsum and Reimbursable projects. Work on maintenance projects. Start planning in 2004.

Experience Hours (Planning & Scheduling): 
11000
Experience Hours (Cost Management): 
11000

Project Planner, Avec, Construction of Arya Sasol Plant in Iran

START Date: 
March, 2006
END Date: 
September, 2007

Member of planning team - Construction of Arya Sasol plant (9th olefin) in Iran

I am working as planner since Mar 2006. My first experience was in a construction project. At that period, a big petrochemical plant was being built in Iran. This plant was a joint-venture of an Iranian Company and a South African company (Sasol). I was responsible for preparing reports, controlling the progress via site visit, preparing and controlling schedule for Civil and Piping Disciplines.

Project Planner, Placabi, Expansion of a Refinery - Construction Phase

START Date: 
January, 2008
END Date: 
July, 2008

Planner of civil discipline - Expansion of Arak Refinery - Iran

In Jan 2008, I became involved in a construction project. I was working for Civil Contractor and I prepared and controlled the schedule with Primavera 3.1.

Project Planner, Network Rail, National Level Crossings

START Date: 
March, 2008

 

In this role I’ve experienced the application of project planning, managing a portfolio to an approximate annual value of £150 million. I’ve developed Project Plans from Development, through into realisation, to handover and project close out, including monthly performance reporting to the Project team. I’ve acted in a supervisor role within the Project Planning team. Toolset used primarily has been Primavera P3e version 5, Microsoft Project 2007 and MS Excel for financial data analysis. 

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content