Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Value Performance Index

5 replies [Last post]
Vaish Asaithambi
User offline. Last seen 13 years 16 weeks ago. Offline
Joined: 1 Feb 2004
Posts: 6
Groups: None
Value Performance Index - Any one know what it is and is there any formulae for that.

Thanks

Replies

Peter Holroyd
User offline. Last seen 1 week 4 days ago. Offline
Joined: 6 Jun 2005
Posts: 162
George,
if the 96.5% is an accum SPI against the baseline which you feel is realistic (and you done already done a resonable amount of work to make the numbers real)
and
you have looked at the top 5 critical paths and everyboby working on todays critcal activities is fully aware and committed to delivering them on time
and
the Float Trend Analysis looks OK
and
your not counting out of sequence progress
and
the programme is suddenly not calling for a step change in performance
then go on, take them out for a drink and put it on expenses. You’ll need the Quodos when the going gets tough !
Luca Basile
User offline. Last seen 9 years 33 weeks ago. Offline
Joined: 10 Jul 2003
Posts: 288
Groups: TILOS
Pay attention.
There are not vitual limit to the SPI value.
At the end of the project it will be always 1.00 (as you will have performed all the scope)
It is "valid" between the 15 and 75% of the project progress
When the project is <15% there are not enought data to have a statistical meanfull population for EV when progress>75% it tends to 1.00.

Been SPI = Earned / planned
you may have performed activity out of sequence and Earned a value bigger than the planned thanks to non critical activity.
It will give you a SPI >1.00 but if you miss a critical activity your project may be in delay.


Hope this help
George Fosana
User offline. Last seen 18 years 5 weeks ago. Offline
Joined: 29 Mar 2003
Posts: 3
Groups: None
I’ve got a 96.5% SPI overall total as of this week. Is there any range of tolerance by how much can we say the progress is OK and not and alarming, i mean what is the maximum SPI value we are allowed to achieve.
Paul Knighting
User offline. Last seen 11 years 40 weeks ago. Offline
Joined: 6 Nov 2002
Posts: 10
Groups: None
If it’s CPI:

BCWP (EV) / ACWP (Actual Cost of Work Performed)

If it’s SPI:

BCWP/BCWS

Hope this helps!
Gary Whitehead
User offline. Last seen 13 years 36 weeks ago. Offline
Joined: 1 Sep 2005
Posts: 69
Groups: None
Would that be the same as Cost Performance Index?

If so, it’s earned value divided by (PPC x planned value)

...i hope.... -it’s been a while...