Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Early Star and Early Finish

2 replies [Last post]
moutaz aldeib
User offline. Last seen 2 years 49 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Dear Planners,

What is the difference between the early start and start? once we enter the durations start and finish are automatically filled but early start and finish no?

Regards,

Moutaz

Replies

omid khan
User offline. Last seen 6 years 2 days ago. Offline
Joined: 3 Jun 2013
Posts: 15
Groups: None

early start:

The earliest possible date the remaining work for the activity can begin.

This date is calculated based on network logic, schedule constraints, and resource availability. Early start dates can change as the project progresses and as changes are made to the project management plan.

  early finish:

The earliest possible date the activity can finish. Early finish dates can change as the project progresses and changes are made to the project management plan.

This date is calculated based on network logic, schedule constraints, and resource availability.

ef=es+duration

 

start(activities):

The current start date of the activity. For started activities, this is the actual start date. For not started activities, this is the planned start date until the project is scheduled. When scheduled, the start date field is set to the remaining early start date.

 

source:

p6 data dictionary 8.1

Arend Woltjer
User offline. Last seen 8 years 45 weeks ago. Offline
Joined: 26 Sep 2011
Posts: 74
Groups: None

Hi moutaz,

 

your answer was very close, it was discussed before on this website.

Please look here:  http://www.planningplanet.com/forums/primavera-version-pm5-pm6/421566/start-finish-vs-early-start-early-finish

 

Cheers,

Arend