Dear All
I am updating the progress for my present project.
the project updation is done for every one month.this is the first month of updation.
the acitivites are task dependant.
duration type- fixed duration and units/time.
% complete type- duration type. resources are assighned with cost also
and i have assigned estimation weights to the WBS LEVEL through top down estimation.
after that when i am recording the progrss for the first month the schedule % complete is 2.5%.
after applying the actual to the activities the actual % complete(whch i have selected as duration % complete) is showing as 6.0%. which is not correct because only those activities which were scheduled are completed.
so by logic both the values should be same.
but the actual % complete is showing more
need your guidance please
thanks in advance