Resources driving activity durations

2 replies [Last post]
Ben Hall
User offline. Last seen 15 years 12 weeks ago. Offline
Joined: 5 Oct 2008
Posts: 30
Hi all,

Does anyone know how to add resources to an activity, where the hours assigned to the resource are less than the duration of the activity?

At the moment, my activity has 114d duration, though when i add my resources they only add up to 25d duration...and this then affect the activity duration. Ie, activity duration changes from 114d to 25d..

Does anyone know how to set up the resources so they dont affect the activity duration??

I have also tried adding another resource which is equal to the activity duration, in this case 114d...though it screws up my Budgeted Labour Units!!

can anyone help me?
Thanks
Ben Hall

Replies

Oliver Melling
User offline. Last seen 5 years 22 weeks ago. Offline
Joined: 24 Apr 2007
Posts: 595
Groups: The GrapeVine
Change the duration type to fixed duration and units.
P6 Support
User offline. Last seen 15 years 43 weeks ago. Offline
Joined: 6 May 2009
Posts: 4
Groups: None
Try switching off ’DRIVE ACTIVITY DATES’at the resource assignment level