RESOURCE DRIVING PROJECT

2 replies [Last post]
Suresh Sankaranku...
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 30 Jul 2006
Posts: 77
Hi friends,
I am new to using the resource driven project. I am working on P5. My companie’s projects are resource driven. If there is no resource available for some period the project duration will extend. Each resource is dedicated for each projects. I know in p3 proj.planner it was working fine but p5 i dont see any changes. In the project view i checked on "Drive activity dates by default". But still i couldnt see any difference. If anyone can explain this topic in detail would be highly appreciated. I hope Dieter can give me solid idea.

Thanks a lot for everyone.
Regards
Suresh

Replies

Suresh Sankaranku...
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 30 Jul 2006
Posts: 77
Dear Imaran,
Thank you very much. Yup that is the one i forgot.. "Instead of Task Dependent" we suppose to give " Resource Dependent"

Many many thanks.
Suresh
Imran Arshad
User offline. Last seen 6 years 3 weeks ago. Offline
Joined: 6 Nov 2007
Posts: 46
Dear Suresh,
For resource driven project setting got to project window,click on Defaults tab then define percent complete as Units & activity type as resource dependent before adding activities in your project.Hope this will help.


Imran Arshad