How Extract Budget Labor Units Time Based

2 replies [Last post]
Horlen Astudillo
User offline. Last seen 16 years 24 weeks ago. Offline
Joined: 3 Jan 2008
Posts: 6
Hello,

I would like to know how export to Ms Excel, the Budget Labor Units Time Based (for S-Curves prourposes). I had tried makeing some reports but It retived the data sumarized, not time based. If posible define many time periods e.g. days, weeks, months, etc.?

I will appreciate some help.

Regards,

Replies

Horlen Astudillo
User offline. Last seen 16 years 24 weeks ago. Offline
Joined: 3 Jan 2008
Posts: 6
Thanks Dieter

Much Appreciate.
Dieter Wambach
User offline. Last seen 7 years 23 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Horlen
When you create a new report you’ll have to make a choice for the area. In this window select "Time distributed data". There will be less areas but you can select your data by days, weeks,..
Regards
Dieter