Resources

1 reply [Last post]
rajesh anand
User offline. Last seen 15 years 9 weeks ago. Offline
Joined: 5 Dec 2006
Posts: 27

In P3
When I give the Resources from
Data
Resources
Mechanical Engineer

Limits
Normal Max
1 2

I want to know why we use 1 for Normal and maximum 2. Please do clarify my doubt? Please reply.

With Regards,
Rajesh

Replies

Mangesh Khuspe
User offline. Last seen 50 weeks 2 days ago. Offline
Joined: 10 Apr 2007
Posts: 162
hi
Rajesh its like that, if you want to assign a resource to any activity, it has to be atleast 1 in quantity, it cant be zero, if you want to spend money u have to have that, otherwise u cant spend.
maximum u can give the no u want per day that is available.
i.e. the limit that resource would be available on any particular day.

cheers

mangesh