RESOURCE LEVELLING

1 reply [Last post]
PAUL WATER
User offline. Last seen 17 years 7 weeks ago. Offline
Joined: 6 Jun 2007
Posts: 18
Groups: None
For resource change from one set of activities to another set of activities I started from resource usage spreadsheet, current project resource, then sorted by Resource ID, in the current project set the actuals 0 and fill down 0 for the current project’s set of activities. Can anyone please write me the steps for resource changes from one set of activities to another? I am missing some step?

Replies

Niek Zonneveld
User offline. Last seen 2 years 25 weeks ago. Offline
Joined: 17 Mar 2005
Posts: 188
Groups: None
Paul,

Have you considered using global change for this?

Furthermore a note of caution. Be aware that you need to treat in-progress activities differently than non-started activities,

HTH