All
We are currently setting up Primavera Version 5, and we need a little advise:-
Scenario:-
We are creating many projects that utilises the same Type of resources, Lets call them fitters.
These fitters, although the same trade are at different sites, and thus are on different projects.
The agreed number of fitters on one project may be 15, and on the other may be 20. Also they may work different shift patterns. i.e. one may have a calendar of 2 shifts x 10 hours x 7 days and the other site 1 shift x 10 hours x 7 days
Question/Problem:-
If we use the same resource name we have to re-set the number of resources each time we change projects, for levelling.
Is there any way to set the limit/available resource for a specific project,
Or is it best to have differently named resource name for each project ? i.e. Site1_Fitter or Site2_Fitter ?
Thanks In anticipation
Replies