Generate Plan % from P3

1 reply [Last post]
wilfred datinguinoo
User offline. Last seen 18 years 42 weeks ago. Offline
Joined: 14 Feb 2004
Posts: 20
Guys need your help,

How can i show plan percentage from P3?
And How can i be delayed in progress let say 50% if we think and the actual delayed is only 10 percent hence
on the schedule is we are not that too far.
Is there a bug in P3?

Thanks in advance guys

wilfred

Replies

Paul Harris
User offline. Last seen 1 year 48 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618
On way is take a copy of the original project and autostatus it using Progress Spotlights. This schedule then may be shown as a second target and Target 2 % Complete displayed.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au